Donegal wind farm planning details in 2016

ballyshannon-windfarm-and-house2

For the second year in a row the number of wind turbines granted permission in county Donegal (24) was lower than the number refused (52).  This is a continuation of a significant trend for such decisions; with the total number of turbines refused permission in 2016 (52) being just one more than the combined total (51) of refusals for the two prior years 2014 and 2015.

Wind turbine permissions for Donegal, per year

Decision/Year

2012 2013 2014 2015 2016

Granted

87 67 94 11

24

Refused

5 7 19 32

52

Withdrawn   1 4

 

Detail in relation to wind farm and ancillary development decisions

There were a total of 31 planning determinations, dealing with wind farms and ancillary developments in Donegal concluded during 2016.  Of these applications six were deemed invalid by Donegal County Council.  A total of seven applications were granted for turbines, totalling 24 turbines, and three applications were refused for a total of 52 turbines.  Of the permissions granted two were extensions of duration.

Three windmasts were granted permission (two being retentions).  One section 5 referral and one pre-application consultation were also determined by to An Bord Pleanála during the year.  Further applications determined and granted related to grid connections, substations and amendments to hardstands.  These decisions are most troubling as they clearly demonstrate the prior wind farm permissions and the necessary assessments were significantly flawed by either failing to include or minimising significant elements from the original applications.  Such project splitting and the unwillingness of An Bord Pleanála to adequately reassess applications under Environmental Impact Assessment laws are a growing concern.

One further point to note is that the continued uncertainty in Donegal in relation to the Wind Energy elements of the County Development Plan, in particular the ongoing court action being take by Cllr. John Campbell is adding to growing community and industry anxiety over wind farm planning in the County; with the issue of zoning and safe setbacks from homes to wind farms remaining in legal and planning limbo.

Note: current live applications for wind farms and ancillary developments in Donegal can be found here, and a link to the wind turbine planning permissions for Donegal in 2014, 2015 are here and here.

The featured image was taken by Matt Britton at a wind farm near Ballyshannon, Co. Donegal – see @britpix on twitter.

Table of wind farm and ancillary development decisions in Donegal 2016

Name

Location Turbines Reference no. Type of App. Status

Decision Date

Carrickaduff Windfarm

Planree Ltd

Between Barnes and Killygordon 49

ABP: PA0040

Full PP REFUSED

25 March 2016

Clogheravaddy Wind Farm Ltd

Frosses 7

DCC: 14/51305

ABP: PL05E.244417

Full PP GRANTED

19 February 2016

Clogheravaddy wind Ltd

Binbane Grid Connection

DCC: 16/50440

Full PP INVALID

6 April 2016

Clogheravaddy wind Ltd

Binbane Grid Connection

DCC: 16/50473

ABP: PL05 .246851

Full PP DCC: Refused

ABP: GRANTED

DCC: 8 June 2016

ABP: 24 Nov 2016

Connective Energy Holdings Ltd

Meenagrauv

Ballybofey

1

DCC: 15/51071

Full PP GRANTED

15 May 2016

Corvin Wind Ltd

Bauville, Inishowen Substation

DCC: 16/51540

Full PP GRANTED

1 December 2016

Cufgaze Limited

Drumnahough and Lenalea Wind Farms to Clogher Substation Substation

&

Grid Connection

ABP: VC0097

Pre-App consultation Is not strategic infrastructure

20 October 2016

Cunard Asset Management

Meenhore

Grousehall

2

DCC: 16/50040

Full PP INVALID

21 January 2016

Cunard Asset Management

Meenhore

Grousehall

2

DCC: 16/50209

Full PP INVALID

11 April 2016

Cunard Asset Management

Meenhore

Grousehall

2

DCC: 16/50209

Full PP REFUSED

15 June 2016

Declan Clarke

Kinnegoe Bay 1

DCC: 15/51683

ABP: PL05.246265

Full PP REFUSED

12 July 2016

Derrykillew Community Windfarm Ltd

Derrykillew

Ballyshannon

5

DCC: 14/51400

ABP: PL05E.245108

Full PP GRANTED

18 March 2016

ESB Networks and EirGrid PLC

Donegal 110kv Alter 110kv line

ABP: PL05.VM0010

Full PP GRANTED

11 May 2016

ESB

Sorn Hill Station & Transformer

DCC: 16/50829

Extend Duration GRANTED

21 July 2016

Gineadóir Gaoith Teoranta

Cronalaght Substation

DCC:15/51726

Amend PP GRANTED

25 February 2016

Gineadior Gaoithe Teo.

Gweedore 5

DCC: 16/50989

ABP: PL05.247194

Amend turbines GRANTED

DCC: 18 August 2016

22 December 2016

Glenalla Green Ltd.

Garrymore

Kerrykeel

1

DCC: 16/50297

Extend duration GRANTED

21 April 2016

Karol McElhinney

Aheavagh, Ballybofey 1

DCC: 16/50540

Extend duration GRANTED

16 June 2016

Lettergull Energy Ltd

Raphoe to Listillion Grid connection

DCC: 15/50968

Full PP GRANTED

18 February 2016

Lir Energy Ltd

Gweedore 1

DCC: 16/51532

Full PP INVALID

20 October 2016

Lir Energy Ltd

Gweedore 1

DCC: 16/51486

Full PP INVALID

12 October 2016

Maas Wind Ltd

Maas 11 Hardstands

DCC: 16/50564

ABP: PL05 .246871

Full PP GRANTED

DCC: 10 June 2016

21 December 2016

Planree Ltd

Cornashesk, Killygordon Wind Mast

DCC: 16/50254

Retention GRANTED

21 April 2016

Planree Ltd

Meenbog, Ballybofey Wind Mast

DCC: 16/50348

Retention GRANTED

21 April 2016

Planree Ltd

Ballyarrell Mountain & Lismulladuff, Killygordan 2 met masts

ABP: PL05E.RL3419

s.5 referral Is development

(Not Exempted)

8 February 2016

Planree Ltd

Meenbog, Ballybofey Wind Mast

DCC: 16/50447

Full PP INVALID

7 April 2016

Planree Ltd

Meenbog

Ballybofey

Wind Mast

DCC: 16/50585

Full PP GRANTED

16 June 2016

proVento Ireland PLC

Tullylinn

Pettigoe

4

DCC: 13/51404

ABP: PL05E.245588

Full PP GranTED

30 August 2016

Advertisements

About cawtdonegal

Concerned About Wind Turbines (CAWT) - Donegal View all posts by cawtdonegal

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: